Whether a public energy lender should commit debt finance to a privately sponsored cross-grid transmission link
The public energy infrastructure lending office of a large advanced economy decides whether to back a privately sponsored high-voltage link between two asynchronous grid regions. The log compares a conditional commitment covering most of the construction cost, a minority tranche alongside commercial lenders, deferral until capacity is contracted, and declining. Readers can see how public credit exposure, borrowing-cost pass-through, crowding-in of private capital, equipment lead times and inter-regional reliability trade off when public credit supports merchant transmission.
The options
The question: Should the public energy lender commit debt finance to the privately sponsored cross-grid transmission link: commit to most of the construction cost, commit to a minority share alongside commercial lenders, defer until capacity is contracted, or decline to commit?
Option 1: Commit to most of the construction cost
For
- Financing certainty lets the sponsor reserve converter and transformer manufacturing slots early, which protects the schedule in a constrained equipment market.
- A conditional commitment covering most of the construction cost is the proposed course because the link adds scarce transfer capacity between two asynchronous grids, purely market-driven transmission tends to be under-built, the lower cost of public debt passes through to transmission charges, and the conditions precedent keep the exposure from being drawn until permits, agreements and equipment are secured. A minority tranche alongside commercial lenders is not preferred because commercial lenders are unlikely to take construction risk before capacity is contracted, which would leave a financing gap and delay. Deferring until capacity is contracted is not preferred because it would cost the sponsor its equipment slots and push reliability benefits back by one to two years. Declining is not preferred because the link would probably not be built in a relevant timeframe.
- The director of the lending office takes this decision under authority delegated by the energy minister, on the advice of the office's credit committee and its engineering, environmental and legal review staff.
- Both regional grid operators, the sponsor, the national budget office on the expected subsidy cost of the loan, and host-area local governments and landowner representatives were consulted on the link's need, cost and siting.
- The IEA report Electricity Grids and Secure Energy Transitions states that linking asynchronous grids requires high-voltage direct-current technology, through lines or back-to-back converter stations, and that interconnected grids improve stability, security of supply and flexibility and lower system costs through trade.
- Joskow and Tirole show in their analysis of merchant transmission investment that lumpy investments, imperfect wholesale markets and the behaviour of system operators undermine the efficiency of purely market-driven transmission investment and tend to produce too little of it.
- The decision-maker's public statement estimated electricity cost savings for households and businesses across both grid regions in the tens of billions of USD over the link's life, and attributed several hundred million USD of savings to the lower interest rate of public debt compared with private borrowing. These are the lender's own projections, not independent estimates.
Against
- A single large exposure to one merchant link, before transmission capacity is contracted, concentrates credit risk on the public lender; converter cost overruns or delays would fall largely on public debt.
- Conditional commitments can be withdrawn or allowed to lapse when policy priorities shift, so the financing signal to the sponsor and suppliers is less firm than it appears.
Option 2: Commit to a minority share alongside commercial lenders
For
- Sharing the debt with commercial lenders halves the public exposure and brings independent credit diligence into the structure.
- The IEA report Electricity Grids and Secure Energy Transitions states that linking asynchronous grids requires high-voltage direct-current technology, through lines or back-to-back converter stations, and that interconnected grids improve stability, security of supply and flexibility and lower system costs through trade.
Against
- Commercial lenders may refuse construction risk on an uncontracted merchant link, leaving a financing gap that delays or stalls the project.
- A conditional commitment covering most of the construction cost is the proposed course because the link adds scarce transfer capacity between two asynchronous grids, purely market-driven transmission tends to be under-built, the lower cost of public debt passes through to transmission charges, and the conditions precedent keep the exposure from being drawn until permits, agreements and equipment are secured. A minority tranche alongside commercial lenders is not preferred because commercial lenders are unlikely to take construction risk before capacity is contracted, which would leave a financing gap and delay. Deferring until capacity is contracted is not preferred because it would cost the sponsor its equipment slots and push reliability benefits back by one to two years. Declining is not preferred because the link would probably not be built in a relevant timeframe.
Option 3: Defer until capacity is contracted
For
- Waiting for contracted capacity converts merchant revenue risk into contracted revenue, lowering the expected loss on any later loan.
Against
- Deferral may cost the sponsor its equipment reservations and push reliability benefits back by several winter peaks.
- A conditional commitment covering most of the construction cost is the proposed course because the link adds scarce transfer capacity between two asynchronous grids, purely market-driven transmission tends to be under-built, the lower cost of public debt passes through to transmission charges, and the conditions precedent keep the exposure from being drawn until permits, agreements and equipment are secured. A minority tranche alongside commercial lenders is not preferred because commercial lenders are unlikely to take construction risk before capacity is contracted, which would leave a financing gap and delay. Deferring until capacity is contracted is not preferred because it would cost the sponsor its equipment slots and push reliability benefits back by one to two years. Declining is not preferred because the link would probably not be built in a relevant timeframe.
- The IEA report Electricity Grids and Secure Energy Transitions notes that the construction phase of grid projects depends on manufacturing slots for transformers, cables and high-voltage direct-current valves, which have long production lead times, and that transformer shortages have delayed projects and raised prices.
Option 4: Decline to commit
For
- Declining avoids any public exposure and leaves the project to be financed on purely commercial terms if its economics justify it.
Against
- Without public debt the link may not be built in a relevant timeframe, leaving the two regions with little transfer capacity during extreme weather.
- A conditional commitment covering most of the construction cost is the proposed course because the link adds scarce transfer capacity between two asynchronous grids, purely market-driven transmission tends to be under-built, the lower cost of public debt passes through to transmission charges, and the conditions precedent keep the exposure from being drawn until permits, agreements and equipment are secured. A minority tranche alongside commercial lenders is not preferred because commercial lenders are unlikely to take construction risk before capacity is contracted, which would leave a financing gap and delay. Deferring until capacity is contracted is not preferred because it would cost the sponsor its equipment slots and push reliability benefits back by one to two years. Declining is not preferred because the link would probably not be built in a relevant timeframe.
- Joskow and Tirole show in their analysis of merchant transmission investment that lumpy investments, imperfect wholesale markets and the behaviour of system operators undermine the efficiency of purely market-driven transmission investment and tend to produce too little of it.
Criteria and values
| Criterion | Option 1 | Option 2 | Option 3 | Option 4 |
|---|---|---|---|---|
| Borrowing-cost advantage to the project | substantial | modest | none | none |
| Expected time to commercial operation | 7 year | — | 9 year | — |
| Credit risk retained by the public lender | high | moderate | low | low |
| Private capital mobilised | low | high | moderate | — |
| Public credit exposure at commitment | 3,000,000,000 USD | 1,800,000,000 USD | 0 USD | 0 USD |
| Contribution to inter-regional reliability | high | moderate | moderate | low |
Evidence
Sources
- https://iea.blob.core.windows.net/assets/ea2ff609-8180-4312-8de9-494bcf21696d/ElectricityGridsandSecureEnergyTransitions.pdf
- https://www.nber.org/papers/w9534.pdf
- https://www.imf.org/-/media/files/publications/howtonotes/howtonote1706.pdf.md