Where and how to add AI-grade package substrate capacity for the 2028 demand window

Open in the app

By · Published

Reconstructs a component manufacturer’s choice of how to expand FC-BGA substrate capacity for AI accelerators ahead of a forecast 2027 to 2028 shortage. It compares domestic, overseas, phased and glas...

The options

The question: How should the company add capacity for high-end flip-chip ball grid array (FC-BGA) substrates for AI accelerators and servers ahead of the forecast 2027 to 2028 shortage: a large customer-backed expansion at its existing domestic site, the same capacity placed at its Southeast Asian subsidiary, a smaller phased domestic expansion without customer commitments, or a shift of capital toward next-generation glass-core substrates?

Option 1: Customer-backed large expansion at the existing domestic site

For

  • Reporting on the regulatory disclosure states an investment of KRW 4.27 trillion in the domestic site from September 2026 to May 2028, with mass production from September 2028, described by the company as its largest-ever investment in a single product and reported as 43.6 percent of 2025 shareholders' equity.
  • The company states that customers will provide part of the funding for the new facilities and guarantee mid- to long-term volumes. Korean technology press reports that this is intended to offset capital-expenditure risk and secure plant utilisation.
  • On the same day as the domestic decision, the company disclosed a separate KRW 2.51 trillion equipment investment for its Southeast Asian subsidiary running to April 2028, bringing the combined announcement to KRW 6.78 trillion.
  • In April 2026 the company's chief executive stated that customer demand exceeded its current production capacity by more than 50 percent. Trade reporting at the time put the combined share of the leading Japanese and Taiwanese substrate makers above 70 percent of the global market.

Against

  • Spending is committed under 2026 market conditions while output arrives into unknown 2028 conditions. Analyst commentary notes the roughly 24-month gap reflects cleanroom construction, tool procurement and qualification cycles, leaving little room for mid-course correction.
  • Capacity arriving in September 2028 lands late in the forecast shortage window, when competitors' announced expansions are also coming on stream; if the gap closes faster than forecast, prices and utilisation fall and the company carries a very large fixed-cost base.
  • Competitors are also expanding: a leading Taiwanese substrate maker targets a 30 to 40 percent increase in capacity by 2027 with new plants from late 2027 and 2028, and a leading Japanese maker targets 2.5 times capacity at one plant by 2028, according to a September 2026 market report.

Option 2: Equivalent expansion at the Southeast Asian subsidiary

For

  • The subsidiary has been expanded for FC-BGA production since at least April 2026, when trade reporting described a KRW 1.8 trillion investment there to serve AI-chip customers, so the company has recent experience of building and ramping capacity at that site.
  • On the same day as the domestic decision, the company disclosed a separate KRW 2.51 trillion equipment investment for its Southeast Asian subsidiary running to April 2028, bringing the combined announcement to KRW 6.78 trillion.
  • It is inferred that lower labour and operating costs at the Southeast Asian site would improve unit margins over the plant's life; the company's disclosures do not quantify the difference.

Against

  • Spending is committed under 2026 market conditions while output arrives into unknown 2028 conditions. Analyst commentary notes the roughly 24-month gap reflects cleanroom construction, tool procurement and qualification cycles, leaving little room for mid-course correction.
  • Placing both new tranches at one overseas site concentrates operational, logistics and geopolitical exposure precisely where customers are asking for supply-chain stability.
  • Competitors are also expanding: a leading Taiwanese substrate maker targets a 30 to 40 percent increase in capacity by 2027 with new plants from late 2027 and 2028, and a leading Japanese maker targets 2.5 times capacity at one plant by 2028, according to a September 2026 market report.

Option 3: Phased smaller domestic expansion without customer commitments

For

  • Phasing keeps the company's balance sheet lighter and lets it respond to evidence on competitor capacity and AI-server demand before committing later phases.
  • Spending is committed under 2026 market conditions while output arrives into unknown 2028 conditions. Analyst commentary notes the roughly 24-month gap reflects cleanroom construction, tool procurement and qualification cycles, leaving little room for mid-course correction.
  • Competitors are also expanding: a leading Taiwanese substrate maker targets a 30 to 40 percent increase in capacity by 2027 with new plants from late 2027 and 2028, and a leading Japanese maker targets 2.5 times capacity at one plant by 2028, according to a September 2026 market report.

Against

  • Declining customer co-funding leaves the full cost with the company, and a later entrant offering only phased capacity risks losing the design-in positions that anchor customers are allocating now, which are hard to regain in later product generations.

Option 4: Capital shifted toward glass-core substrates

For

  • A July 2026 market-research report describes a planned glass-core joint venture with about KRW 480 billion in capital, a 66 percent stake for the company and full-scale operations from the second half of 2027. It reports measured gains in flatness, thermal expansion and stiffness for glass cores, but notes that key manufacturing hurdles remain and that commercial-scale adoption is expected after 2030.

Against

  • Holding back organic capacity during the widest part of the forecast shortage would cede share to incumbents that are expanding, and the glass-core roadmap already has its own funded joint venture, so this option adds little that the parallel programme does not already provide.

Criteria and values

CriterionOption 1Option 2Option 3Option 4
Capacity producing in the 2028 shortage window (higher is better)fullfullpartialnone
Gross capital commitment relative to equity (lower is better)high—moderatelow
Demand certainty for the new capacity (higher is better)highmoderatemoderatelow
Months to volume production (lower is better)24 month24 month24 month48 month
Reversibility after commitment (higher is better)lowlowhighmoderate
Supply security offered to customers (higher is better)highmoderatemoderatelow
Technology and qualification risk (lower is better)lowmoderatelowhigh